Neryungri Water

Four years as sole consultant to the Neryungri city water utility in Yakutia — PIU establishment, full-cycle EBRD procurement, disbursement and construction supervision.

Completed
Insulated above-ground water pipes running toward apartment blocks in Neryungri
Neryungri, Republic of Sakha (Yakutia), Russian Federation
ClientJSC Nerungrinsky Gorodskoy Vodokanal (NGVK), Republic of Sakha (Yakutia)
Financed byEBRD — project 43958
Period2015 → 2019 · completed
CountryRussia
SectorWater & Wastewater
Our roleSole consultant — full assignment
DeliverySole consultant
fig. 01 — background

Why this project exists

Neryungri is a coal-mining city in southern Yakutia, where winter design temperatures make water infrastructure a different discipline: everything runs above ground, insulated, and downtime is not an option.

The EBRD financed the modernization of the city's water sector, with the municipal utility JSC NGVK as borrower. Forlog was engaged as the sole consultant for implementation support and construction supervision — the whole assignment, carried in-house.

The utility's closing reference is the kind worth keeping: the contract was “implemented in full”, with “no complaints or remarks”.

scope of services
fig. 02 — the assignment

What the consultant is engaged to do

  • Establish the PIU from scratch: functions, organisational structure, staff schedule, job descriptions
  • Training-needs analysis and capacity building for PIU staff
  • Design assistance and development of technical specifications
  • Full-cycle procurement of goods, works and services under EBRD Procurement Policies & Rules
  • Compliance with the financing documents, reporting, and timely, targeted disbursement of project funds
  • Contract administration and technical and construction supervision — FIDIC engineer services
  • Stakeholder coordination, the Project Steering Committee, permits and approvals

“FORLOG AG implemented the contract in full. JSC NGVK has no complaints or remarks.”