If your firm wants engineering work in Central Asia or the Caucasus, start looking a year or two before you expect to see a tender. That gives you time to decide which assignment you want and to meet the people you’d need on the ground. Both decisions are harder once the submission clock is running.
Follow the programme, the loan and the individual contracts
Start with the investment programme. A city may have a plan to improve wastewater services across several districts. Follow the projects that come out of it and find out which utility or authority is responsible for each one. If your firm designs treatment plants, find out whether the proposed investment includes a plant and whether the design is likely to be bought separately. Record the project and the package you’re interested in. Update your plan when the scope or timetable changes.
When a project appears in the EBRD pipeline, read the project summary. Concept review is an early milestone. The Bank and the client then develop the financing and carry out due diligence. The project goes through final review and approval before the loan agreement is signed. Check the published status as the project progresses. By the time of signing, you want to know who will procure the assignment and where it will be advertised. Watch the client’s procurement plan and general procurement notice, when available, and follow the individual notices on the EBRD Client e-Procurement Portal (ECEPP). Start checking before signing, since a client may begin some procurements in advance. EBRD project pipeline · EBRD financing process · EBRD procurement rules on advance procurement
Who hires the consultant at each stage?
The project owner can hire an owner’s engineer or technical adviser while the concept is still being developed. That adviser works for the owner. On a water project, the job might be to check the utility’s demand estimates, compare treatment options and help define the scope the owner takes to a lender.
The EBRD can also commission consulting work for its own project preparation. A feasibility assignment might test whether the proposed solution is technically viable and what it would cost to build and operate. When the Bank contracts the consultant directly, follow the Bank’s own consultancy opportunities and the instructions in its notice. EBRD infrastructure project preparation · EBRD corporate procurement and consultancy services
Once financing is signed, the client typically procures the consulting packages it needs to deliver the project. Those might cover detailed design, support to the project implementation unit or supervision of the works. The EBRD’s summary for the Kyrgyzstan Climate Resilience Water Supply Project shows how this can look on one project. It lists a feasibility and hydrology study before loan signing and a separate design and engineering supervision assignment after signing. A firm interested in supervision could start checking the likely scope and identifying site staff while following the earlier study. Kyrgyzstan Climate Resilience Water Supply Project
The first assignment examined water availability and whether the irrigation works were feasible. If your firm wants the later supervision role, use this time to identify engineers who could work on site.
The agreement finances the project. The client procures the engineering work separately. Start watching the client’s notices early, because procurement can begin before the loan is signed.
The project plan lists a separate consulting assignment for this work after the loan agreement. When the tender appears, check which specialists the client needs and how much time they must spend on site.
A project can have several tenders once it moves into delivery. On Kyrgyzstan’s Electricity Supply Digitalization Project, the national grid operator needed 210,000 household smart meters. In August 2025, Forlog and GIE LTD signed a consulting contract with the utility that included preparing the equipment tender and supervising the supply contracts. Equipment suppliers and consultants had different packages to watch under the same investment. Forlog project record · EBRD award notice
Check whether early work affects later eligibility
Before you accept a feasibility study or an owner’s engineer role, identify which later contracts your company might want to pursue. Read the proposed terms and check what your team would be responsible for. If you help write the specifications for a later contract or have access to project information that other bidders won’t receive, you may be excluded from that competition. A later role can also raise a conflict if it requires an independent review of work your firm carried out. Ask your proposed partners about their earlier involvement too. The issue can arise through a member of your team. EBRD eligibility and rejection grounds · EBRD standard procurement documents
If the downstream contract is the one you want, resolve that question before committing to the upstream work. Where procurement documents have been issued, disclose the earlier role as required and use the formal written clarification process if eligibility is unclear. Explain what your firm did and what information it received. Put the question to the procuring entity before you spend money building the proposal.
Find out what the first deadline requires
Read the notice with the instructions and data sheet. The procurement procedure determines what you’ll have to submit and when. The evaluation method tells you how the client will assess the submission. Check the version of the rules identified in the documents for that assignment. EBRD procurement policies and documents
- Expression of interest
- Evidence that the firm qualifies for the shortlist. Check which references and partner details the notice requests.
- Single-stage selection
- A technical proposal and a financial offer, both due by the same deadline.
- Multi-stage selection
- The client may ask for an unpriced technical proposal first and invite priced proposals later.
Expression of interest and shortlisting
An expression of interest (EOI) is often the first step in shortlisting consulting firms. The client is deciding whom to invite to submit a proposal. Check what it asks you to show at that stage. It may want a set of comparable firm references, financial information or details of the association you propose. If the notice asks for a partner commitment or named experts, get that evidence before you submit. EBRD prequalification documents
The cost and commitment of responding are usually modest compared with a full proposal. You may have enough to put in a credible EOI while you’re still working out the detailed staffing schedule and fee. Use the time after the EOI to confirm who can do the work and test the likely cost. If shortlisted, read the request for proposals as soon as it arrives and make a fresh decision about whether to proceed. That is when you may see the full terms of reference or discover how much effort the client expects on site. Check any restrictions on changing the team after shortlisting before assuming you can add or replace a partner.
Single-stage competitive selection
When the notice calls for a full proposal in one stage, the technical and financial offers share a deadline. You need a methodology and a priced work plan based on confirmed staff by that date. Under the two-envelope procedure, both offers are submitted together in separate envelopes or their electronic equivalent. The client evaluates the technical offer first. If the documents specify a minimum technical score, check how that threshold affects which financial offers are opened. Read the evaluation criteria before you decide where to put your strongest people. After evaluation, the client may invite the selected firm to negotiate or finalise the contract, as provided for in the procurement documents. EBRD single-stage, two-envelope procedure
Multi-stage competitive selection
For a complex consulting assignment, the client may ask for an initial unpriced proposal. That can require a substantive technical response. The client reviews the approach and may seek clarifications or refine the requirements. It then invites final priced proposals. Allow for the work involved in revising the method and schedule between stages. Keep a record of the changes so the final fee covers the final scope. EBRD multi-stage procedure
The rules also allow direct contracting in specific circumstances, such as where continuity is justified and the applicable conditions are met. For competitive selection, use the published evaluation method to see how quality and cost count. Check whether the stated budget is a ceiling or an estimate and whether the technical criteria reward particular experience or delivery methods. EBRD procurement rules on selection procedures · EBRD rated criteria
Start with turnover and references, then build the team
Turnover. If there’s a minimum turnover requirement, check it before you start writing. Identify the financial years the client will count, the evidence it accepts and whether the figure applies to the whole joint venture, its lead member or each partner. Check whether it asks for total turnover or turnover in relevant services. A partner with a strong balance sheet may still leave a gap if the lead has to meet its own threshold. Give finance enough time to obtain the accounts and confirm any required currency conversions. EBRD consultancy qualification criteria
Firm references. Read what the client means by similar work. A completed design assignment may satisfy a design criterion and leave a gap if the client also wants construction supervision. Check the required period, contract size and evidence of completion where specified. For work delivered in a consortium, write down the share and scope your firm actually delivered. Check whose references will count if you bring in a joint venture member or a subconsultant. Where the client asks for comparable local or regional work, name the assignment and explain what your team did there. EBRD consultancy qualification criteria
Local partners and experts. This is often the hardest part, and in our experience it deserves the most time. Meet potential partners well before the notice. Ask for a comparable assignment and speak to the people who delivered it. Where you can, get a reference from the client that hired them. Find out who would attend site meetings and whether they can work in the language the client needs. If a key expert is already tied to another site, the partner’s company references won’t cover the gap. Agree what each firm will deliver and who will be responsible for the local team. Settle how the local team will be paid. Then check the named experts’ CVs against the tender requirements and confirm their availability for the periods in the work plan.
Technical proposal and schedule. Read the terms of reference alongside the evaluation criteria. Explain the engineering approach you’d use and why it suits the site and the client’s operating constraints. Work backwards from the deliverables and assign someone to each one. For a treatment plant, a locally based engineer might cover routine site inspections while a Swiss process specialist reviews the contractor’s design and attends commissioning. Decide when that specialist must be on site and who can act between visits. State what data or access the client needs to provide and ask for clarification if something essential is missing. The days in the staffing schedule should agree with the method described in the technical offer and the fees in the financial offer. EBRD consultancy proposal requirements
Budget and competition. Look up comparable awards to see which firms win work of this kind and at what contract value. Compare the scope and duration before treating an award value as a benchmark. If the assignment budget is undisclosed, those awards give you a starting point for testing your own estimate. Build your price from the work schedule using the number of days at local and Swiss rates. Add travel and other costs the contract puts on you. Check how the documents treat reimbursable expenses and taxes. If you’re over budget, look again at when you need people on site and where remote review is acceptable under the terms of reference. Keep enough time for the people who will carry the responsibility. If the resulting fee still looks uncompetitive, you have a reason to pass on the tender before the team loses days to drafting. EBRD procurement and award notices
Decide whether the full bid is worth the upfront cost
Budget for preparing the proposal as soon as you start assessing the opportunity. Estimate the days your technical lead and partners will spend on the bid and put a cost against them. Include the time for checking the price and chasing signatures. Add any outside costs, such as translations or a site visit. That work has a cost whether you win or lose, and it comes out of the same staff capacity you need for paying assignments. A favourable response to an EOI may make a bid worth considering. It’s also the point to recheck the scope, the likely competition and your fee against what you know after shortlisting. For a single-stage tender, make the same decision before starting the first submission.
We’d commit to a full bid where we can show that the team qualifies, staff the job on the terms proposed and point to something that would score well against the likely competition. If an essential reference is missing, the right experts are committed elsewhere or the fee only works on doubtful assumptions about site coverage, stop and reassess. Even a bid you’ve worked hard on can lose. Concentrate your proposal budget on the opportunities where you have a credible chance of winning.
Give someone responsibility for the submission
On a consortium bid, the partners need to agree early on who can sign the tender letter on their behalf. Any powers of attorney have to be ready by submission. When a bank needs to issue a tender security, its lead time goes into the bid schedule too. We recommend agreeing at the start who will provide each document listed in the tender’s data sheet and when it’s due.
For the final review, we’d use the files ready for upload. The signed letter should be in the package, and the forms should reflect any amendments from the client. If the technical and financial offers go in separately, prices stay in the financial offer. The client may ask about a minor omission. It can reject a bid over an unsigned letter or a missing tender security or a financial offer placed in the wrong package. EBRD submission instructions · EBRD standard forms
We recommend giving an IFI procurement specialist responsibility for the submission. They follow up with the partners and make sure everyone works from the same instructions when the client answers questions or changes the documents. Whoever submits also needs to know that their portal login works and what the stated closing time means in Switzerland. We’d leave enough time to confirm the portal has received the bid before it closes.
Talk to Forlog about an EBRD project
We’ve worked on EBRD-financed projects since our early days, and 100% of Forlog’s revenue comes from IFI-financed projects. Forlog can review the opportunity with you before you spend on a proposal. If you decide to pursue it, we can lead the bid process. We’ll coordinate inputs and manage the compliance review through to submission. We can also train your team on a live bid so they know what to check and when for the next one. Send us the notice or the project you’ve been following and tell us where you’d like advice. Write to Forlog